Project Description
Rotonda West MSBU has 17 bridges needing design services to implement the FDOT maintenance and repair items for each of the respective bridges.
This project is for design services for bridge rehabiliations - Bridges #014098 and #014099
Rotonda Circle over Pebble Creek - Bridge #014098
Rebel Court over Rotonda River - Bridge #014099
Project Location
Rotonda Circle over Pebble Creek - Bridge #014098
Rebel Court over Rotonda River - Bridge #014099
See Location Map below.
Latest Updates
Upcoming Project Activities March 2024
Construction bids were opened and Villa Fuerte Construction was the lowest bidder with an approved contract from the Board of County Commissioners.
Bridge #014098 (Rotonda Circle over Pebble Creek) will be completed and the lane closure open to traffic on March 22, 2024.
Construction will begin on March 26, 2024, with bridge #014099 (Rebel Court over Rotonda River), this bridge should be completed on May 5, 2024. This bridge will have a temporary lane closure until the bridge construction is complete.
Please exercise caution when traveling in the vicinity of construction zones.
Budget
Phase | Cost |
---|---|
Design | $134,770 |
Construction | $709,281.30 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 05/25/2022 | 06/30/2022 | |
Design Development | 06/07/2022 | 06/24/2023 | |
Construction | 02/20/2024 | 05/05/2024 |
Supporting Materials
Project Phase
Construction
Last Updated
03/19/2024
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Project Number
2022000429
Sponsor Department
Public Works
Design Engineer/Architect
Bridging Solutions/KCI
Construction Contractor
Villa Fuerte Construction